Sprint 21.03
Fix version | 21.03 |
---|---|
Document status | DRAFT |
Document owner | @Elizabeth Jones |
Designer | @Yaw Nti-Addae |
Tech lead | @Joel Byrnes |
QA | @Elizabeth Jones |
Sprint Goals
Goal | Status | Notes | |
---|---|---|---|
1 | Complete the Job Status UI to allow for easy monitoring of submissions and data download. | inprogress |
|
2 | Complete development of the Web Loader UI MVP | inprogress |
|
3 | Deploy v2.2.3 to CIMMYT (Kate) | todo |
|
4 | Deploy v2.2.3 to ICRISAT (Prasad) | SCHEDULED |
|
5 | Deploy v2.2.3 to ICRISAT (Abhi & Siva) | todo |
|
6 | Deploy new instance to ILCI | todo |
|
7 | Deploy new instance of v3 for Grape project | inprogress | Upgrade to v3
|
8 | Create & prepare tools for release 2.2.4 | todo |
|
9 | Create & prepare deployment scripts to deploy our Flapjack Bytes fork | todo |
|
10 | Complete NGINX Proxy | inprogress |
|
Assumptions
new instances will be ready to install software
Tasks
Requirement | User Story | Importance | Jira Issue | Notes | |
---|---|---|---|---|---|
1 | Complete Job Status UI | HIGH |
|
| |
2 | loader UI tasks | https://gobiiproject.atlassian.net/browse/GWEB-339 https://gobiiproject.atlassian.net/browse/GWEB-307 https://gobiiproject.atlassian.net/browse/GWEB-340 |
|
|
|
3 | Deploy v2.2.3 for CIMMYT (Kate) |
|
| assist with upgrade to v2.2.3 | |
4 | Deploy v2.2.3 for ICRISAT (Prasad) |
|
| assist with upgrade to v2.2.3 | |
5 | Deploy v2.2.3 for ICRISAT (Abhi & Siva) |
|
| assist with upgrade to v2.2.3 | |
6 | Deploy v2.2.3 for cloud demo instance |
|
| The cloud demo site is out of date and needs to be updated to v2.2.3 once it is finalized. | |
7 | Deploy v3 for Grape project |
|
| Once the environment is prepared, install & configure the latest v3 software stack for a grape crop. | |
8 | (upcoming v2.2.4 tasks) |
|
| Create necessary bash scripts / Jenkins configuration to provide tools for hotfix to v2.2.4 | |
9 | Create Flapjack Bytes deployment scripts |
|
| Create necessary bash scripts / Jenkins configuration to provide tools for simple install of Flapjack Bytes. | |
10 | Complete NGINX Proxy |
|
|
|
User interaction and design
App | Link |
---|---|
LoaderUI mockup | |
LoaderUI dev env | |
Job status mockup |
Open Questions
Question | Answer | Date Answered |
---|---|---|
|
Out of Scope
Deploying ICARDA wheat instance
Deploying IITA maize instance
Migrating Bamboo plans to EBS