Page Properties | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Sprint Goals
Goal |
---|
Complete the Job Status UI to allow for easy monitoring of submissions and data download. |
Deploy v2.2.3 to App-test (might be completed before sprint starts) |
Complete development of the Web Loader UI MVP |
Deploy v2.2.3 to CGs:
|
Deploy v2.2.3 to a new cloud demo instance |
Migrate the Flapjack Bytes code repo @ github to the GDM code repo @ bitbucket |
Deploy new instance to ILCI |
Deploy new instance of v3 for Grape project |
Create & prepare tools for release 2.2.4 |
Create & prepare deployment scripts to deploy our Flapjack Bytes fork |
Assumptions
new instances will be ready to install software
Tasks
Requirement | User Story | Importance | Jira Issue | Notes | |||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Complete Job Status UI |
|
| ||||||||||||||||||
2 | Deploy v2.2.3 to App-test | v2.2.3 must be installed on the app-test instance for final testing before release |
|
|
|
|
| ||||||||||||||
3 | (likely upcoming tasks for loader UI) | ||||||||||||||||||||
4 | Deploy v2.2.3 for CIMMYT (Kate) | assist with upgrade to v2.2.3 | |||||||||||||||||||
5 | Deploy v2.2.3 for ICRISAT (Prasad) | assist with upgrade to v2.2.3 | |||||||||||||||||||
6 | Deploy v2.2.3 for ICRISAT (Abhi & Siva) | assist with upgrade to v2.2.3 | |||||||||||||||||||
7 | Deploy v2.2.3 for IRRI (Denis) | assist with upgrade to v2.2.3 | |||||||||||||||||||
8 | Deploy v2.2.3 for cloud demo instance | The cloud demo site is out of date and needs to be updated to v2.2.3 once it is finalized. | |||||||||||||||||||
9 | Migrate Flapjack Bytes repo into bitbucket | Clone the latest flapjack-bytes-loader (and maybe flapjack-bytes) and migrate to bitbucket. Ideally: retain history. | |||||||||||||||||||
10 | Deploy v3 for Grape project | Once the environment is prepared, install & configure the latest v3 software stack for a grape crop. | |||||||||||||||||||
11 | (pending v2.2.4 tasks) | ||||||||||||||||||||
12 | Create Flapjack Bytes deployment scripts | Create necessary bash scripts / Jenkins configuration to provide tools for simple install of Flapjack Bytes. |
User interaction and design
App | Link |
---|---|
LoaderUI mockup | |
LoaderUI dev envXVM23 | |
Job status mockup |
...
Question | Answer | Date Answered |
---|---|---|
Out of Scope
Deploying ICARDA wheat instance
Deploying IITA maize instance
Migrating Bamboo plans to EBS